This contract concerns the construction of a new medical-technical block and a polyclinic on the Joseph Bracops site.
The contract is divided into lots, namely:
• Lot 01: "deviations";
• Lot 02: "demolitions, structural work, completions and surroundings"
• Lot 03: "special techniques"
This contract concerns only lot 1.
Lot 1 - DEVIATIONS includes the realization of all HVAC, Sanitary, Electricity, Sewerage, and Medical Fluids work as part of the diversion of techniques to be carried out before the demolition of the 6 existing buildings G, H, I, K, P and Q.
The project must be carried out in 2 phases:
• Phase 1 - deviation of techniques in an occupied environment.
• Phase 2 - disconnection and dismantling of existing facilities on the edge of the buildings to be demolished, and once the 6 buildings have been evacuated.
See II.1.4