Painting works - Kern Ost.
Painting and painting work on all floors, in the hallways, in the stairwell, in the sanitary rooms, tea kitchens and lounge areas.
The work is carried out in partial areas of the respective floors and on each floor. There may be short-term interruptions in the work between the construction phases.
The work takes place during ongoing operations. Noisy work must not be carried out between 9:00 a.m. and 5:00 p.m.
Approximately 2,440 m
Only personnel who have previously been checked for reliability and have no negative connection points may be used to perform the services.
This procedure is under the allocation no. 20-97550. (Please specify when making inquiries).