A 96 Tunnel Gräfelfing, traffic safety for complete repair of the Gräfelfing Tunnel
The following essential work is to be carried out:
- construction site equipment
• Preparation of traffic sign plans for the application for all traffic law
Arrangements for shorter and longer duration jobs on the motorway
- Preparation of traffic sign plans for the application for traffic law orders for work sites of longer duration, including diversions for the municipal roads Maria-Eich-Straße and Jahnstraße.
- Coordination of traffic sign plans in the course of traffic meetings and revision of traffic sign plans.
- Participation in weekly meetings
- Obtaining all traffic law orders from the responsible road construction authorities or traffic authorities
- Provision of all traffic safety measures for work sites of longer and shorter duration and diversions including provision, maintenance, operation and control as well as temporary traffic safety measures for the establishment and dismantling of traffic safety and diversions
- 3 times on weekdays conversion of the alternating lane (Monday to Friday) and 2 times conversion on Sunday. There will be no renovation on Saturdays and public holidays.
- Control of job security
- Dismantling of traffic safety and diversions