The technical services of the City of Kalajoki request a quote for quarry deliveries of the breakwaters of the Marina marina. The deliveries will take place between September 2023 and December 2025. The total amount of aggregates to be delivered is approximately 280,000 tonnes.
Most of the quarry and stone throwing 600-800 mm deliveries will take place between September 2023 and April 2024. The boulders > 1300 mm and the stone throw 200-400 mm will be delivered mainly between 2024 September and April 2025.
Preliminary estimated delivery volumes:
- Mixed quarry 0/90 quantity 4000 tonnes
- Mixed quarry 0/300 volume 22 000 tonnes
- Mixed quarry 0/600 volume 150 000 tonnes
- Stone throwing 200-400mm quantity 10,000 tons
- Stone throwing 600-800mm quantity 40 000 tons
- Boulders > 1300mm quantity 55 000 tons
The quarries must be mixed quarries in accordance with the tender. The aggregate must not be eroding. When storing and transporting quarry, special attention should be paid to preventing speciation. Excessively fine quarries are returned to the supplier.
The supplier must be able to deliver 1000 – 1500 t/shift. If the supplier is unable to deliver the quantities in question, the customer can immediately procure the aggregates from elsewhere.
More detailed delivery volumes are agreed with the client's management on a daily basis.
As a rule, delivery takes place during normal working hours in the construction industry (Mon-Fri 7-16). Other delivery times will be agreed separately.
The delivery takes place at the Marina construction site at Keskuskarintie 165. Delivery of loads is carried out on the banks of breakwaters, where there is a subscriber reception (excavator).
The delivery area is a construction site where normal practices regarding clothing, equipment and lighting are followed.
Invoicing must be based on acknowledged consignment notes or an electronic system from which delivery volumes can be clearly verified.