FL 11_Fassadenarbeiten
Veröffentlichungstext 92.Grundschule
The 11 Fassadenarbeiten
- approx. 1,900 m2 façade school, flush-mounted, reinforcement, plaster and painting
- approx. 65 m2 curtain wall school with fibre cement panels
- approx. 440 m2 façade sports hall, flush-mounted, reinforcement, plaster and painting
- approx. 20 m2 curtain wall sports hall with fibre cement panels
- approx. 195 m2 ETICS at the new sports hall
For more contract deadlines, see procurement documents
+++ The following documents must be submitted to the issuing body at a separate request:
- breakdown of unit prices according to Form 223,
- original calculation
Content of the original costing: This must be prepared according to the content of form 223 - breakdown of unit prices of ALL items, i.e.: LV item; short description; quantity; unit of measure; time approach; partial costs including additions in euros per unit of measure (wages, substances, devices, other); offered unit price (sum of wages, fabrics, equipment, other) . +++