After completion of the first construction phase, the extension of the middle school (MS) is now taking place in a second construction phase, an increase in
of existing parts, as well as addition of various areas and construction of a break hall between the new building, the gymnasium
and middle school. In addition, the collection of the middle school is to be completely refurbished. For this purpose, the building will be completely
cleared.
The school complex in Wittelsbacher Straße in Germering will be energetically renovated and expanded in several construction phases.
First, the extension for the primary school was completed. At the same time, two gymnasiums and a building wing for lunchtime care - Betreuungsbrücke - were newly built.
Currently, the middle school is being completely renovated, expanded and increased. Between the Mitteschule and the gymnasiums, a break hall covered with a wooden roof is being built.
In the course of the work in the middle school and break hall, the existing locking system is to be supplemented.
The object of the order includes the delivery and installation of the hardware for the expansion of the digital locking system of public institutions of the city of Germering.
The offered components must correspond to a complete system, which is fully compatible with the locking system of the city of Germering
is compatible and can be managed and programmed with the existing software.
Transponder - 50 St.
digital locking cylinder, Europrofil double knob cylinder me under. Requirements – 134 pcs.
digital locking cylinders for mobile partitions – 3 pcs.
Blindzylinder– 57 St.
Digital smart relays incl. power supplies and wireless network – 26 pcs.
Router incl. network modules – 16 pcs.
Events:
Publication of procurement documents: 19.08.2022
Assembly start: 09.01.2023
Completion of installation of locking system: 24.03.2023