In this allocation unit 3 lots are included and are awarded by lot.
Lot 1 Road construction:
Relocation of Klosterstraße via BW 7. The road embankments have already been built. The road superstructure including planum is the subject of the order.
Lot 2 noise barriers 4 and 5 in coordination with road construction and construction phases.
Lot 3 Traffic management: There are several construction phases and dependencies. The individual traffic management phases are presented in the traffic concept of the working group
Lot 1 Road constructionLot 1 includes the construction of the 2 central crossings L523, construction of new Klosterstraße on the already existing dams via BW 7, connection to old Klosterstraße at LSW 5, as well as connection areas at KVP 5 and 4. The planum must be newly manufactured and compacted.
B47n South Bypass Worms, BA 3.3 Lot 2 (LSW 4+5)The LSW 4 is to be produced in 2 stages. 1 section on previous year. Dam and 2 section in the area of the connection Klosterstraße old at LSW 5 after traffic diversion to new Klosterstraße.
Lot 5 in the area of the connection after traffic diversion
B47n Southern bypass Worms, BA 3.3 Lot 3 (traffic management)Create traffic management plans from a traffic concept and set up, maintain, dismantle and control traffic management.