The research and training mine is currently being developed via the two day openings Schacht Alte Elisabeth and Schacht Reiche Zeche. The tonnage shaft Alte Elisabeth acts as a retracting betting opening and can be used for material and (limited) passenger transport. The transport of people and materials for the visitor mine and the research and training mine is carried out via the Reiche Zeche shaft. At the same time, the daylight opening is used as a waste air shaft. In the future, the development of the 3rd level for the removal and preparation of the planned new drivages as well as any rehabilitation measures at the level of the Rothschönberger Stolln is also planned via the shaft. The day openings used are maintained by the TU Bergakademie Freiberg, which also carries out the necessary maintenance and reconstruction measures.
The new ventilation system must be designed in such a way that, in addition to supplying the underground workings at the level of the tunnel floor and the level of the 1st level as well as the visitor mine there, a sufficient ventilation supply for the planned drivages at the level of the 3rd level is ensured in the future.
For the 3rd level, a diesel output of approx. 200 kW and an occupancy of a maximum of 50 employees is planned. As a result of the evaluation, an additional daytime opening is required for the targeted fresh air supply of the drivages at the level of the 3rd level.
Planning Lph 4-8 is based on existing design planning.
The client intends the following planning services
for planning the construction project:
"Ventilation of the research and training mine of the
TU Bergakademie Freiberg"
to be awarded:
- Civil engineering structures Planning services according to HOAI 2021 § 43:
all basic services of work phases 4 – 8
as well as special services according to HOAI Annex 12 to § 43:
- Participation in obtaining the consent of approval authorities and other parties involved in the planning, such as: Oberbergamt, experts, building supervisory authorities (Lph. 4)
- Special achievement: Coordination of the overall project (Lph. 5)
- Special service: Preparation of schedules (Lph. 5)
- Special service: Participation in the examination and evaluation of ancillary offers (Lph. 7)
- Special service: cost control (Lph. 8)
- Special service: Checking supplements (Lph. 8)
- Special service: Markscheiderleistungen, insofar as necessary for the project (Lph. 8)
- Special achievement: Updating of the fracture of the FLB (Lph. 8)
- Special service: Local construction supervision (Lph. 8)
- Special service: supervision of the execution of the construction work (Lph. 8)
- Special service: Participation in the instruction of the contractor in the construction project (construction start-up meeting) (Lph. 8)
- Special service: Monitoring the execution of the object for conformity with the documents released for execution, the construction contract and the specifications of the client (concession documents of the contractor released by SOBA) (Lph. 8)
- Special service: Checking and evaluating the eligibility of supplements (Lph. 8)
- Special service: monitoring the elimination of deficiencies found during the acceptance of the services (Lph. 8)
- Special service: documentation of the construction process (Lph. 8)
- Special service: Participation in the measurement with the executing companies and checking the measurements (Lph. 8)
- Special service: Participation in official inspections (Lph. 8)
- Special service: auditing, comparison of the results of the audit with the order sum (Lph. 8)
- Special service: Participation in monitoring the testing of the functionality of the plant components and the entire plant (Lph. 8)
- Special service: Monitoring of the execution of structures for conformity with the stability certificate
as an optional service (Lph. 8)