Faculty of Veterinary Medicine Oberschleissheim,
OSH_ErschlC2, access to Campus 2
Landscaping:
- Mowing areas (approx. 2,100 m2)
- Dismantling of existing roads and disposal of the resulting material (approx. 1,100 m2)
- Construction of temporary paths for connecting buildings (approx. 280 m2)
- Dismantling of an existing bus turning loop including paved areas and road area (approx. 800 m2)
- Dismantling of an existing bicycle path made of honeycomb paving stones (approx. 400 m2)
- Felling of trees along roads, salvage of woodpecker dens (17 hours, 2 hours caves)
- Construction of temporary bus stops on Veterinärstraße and Sonnenstraße
Bodenschutzplatten (ca. 140 m2), Asphaltprovisorien (ca. 120 m2)