Reconstruction and extension of the town hall - shell, scaffolding, façade
The project will be built in two major construction phases. First of all, in the northern area
of the construction site, the new building was erected. After the relocation of the administration from the directly southern
This old building will then be partially demolished, expanded, and finally connected to the new building.
BUILDING - BUILDING CONSTRUCTIONS
founding
The building will be flat on reinforced concrete base slabs with thickenings for strip and point fdunaments
founded. The new building will have a partial basement to accommodate the building services. The
The lower area is sealed by a WU construction. In the area of the connection of old and
The new building will be underpinned using the HDI jet jet method.
Exterior and interior walls
The load-bearing exterior walls are built as reinforced concrete walls in the area of the northern new building and as
KS-MW walls created in the area of the southern extension. The old building is made of brick or brick.
KS masonry.
The staggered floor will be built in the transition between the old and new buildings in timber panel construction.
The building will be equipped with a façade of light, grey-beige facing masonry and prefabricated elements made of
colored concrete, which take up the horizontal structure of the original old building.
Exterior doors and windows
An aluminium mullion and transom construction is planned for the foyer. All windows and doors
are designed as aluminium tubular frame elements.
The main entrance is integrated into the PR façade on the west side facing the market square. All
further exterior doors such as technical, delivery and escape doors will be installed on the south and west sides in
Light metal construction.
Interior walls
The load-bearing walls are made of reinforced concrete. The non-load-bearing walls are divided into
Masonry, timber panel construction and drywall construction created. In the area of the offices
Wall coverings made of veneered wood-based materials are used.
inner doors
Object doors made of wood-based material or steel, partly in 2-leaf design, with side lights or with
Fire protection requirements T30 or smoke-tight, partly tubular frame doors glazed.
Flooring
Cement screed is laid floating. In the area of offices, a nationwide
Underfloor heating provided. The floor coverings are linoleum, textile/hard covering, and coated
Screed as well as sanded exposed screed provided. In the foyer, the screeds are used as heating screeds
Educated.
Cover
The ceiling above the ground floor is made of reinforced concrete construction and is built on load-bearing interior and
Exterior walls as well as reinforced concrete columns are supported.
hillside ceilings
Almost the entire building will be equipped with special suspended ceilings made of clay modules with integrated
Heating and cooling function. These ceilings are provided with a clay plaster on the underside and
white coated. In the foyer, in favour of acoustic curtain ceilings with fine plaster on these ceilings
renounced.
top, roof
In new and old buildings, the roof structure is designed as purlin roof, partly with steel reinforcements.
The existing roof truss will be used to increase the sill and floor heights in the attic
completely dismantled and replaced.