The subject of the contract is the supply of electricity in the period from 1.1.2020 to 31.12.2020 to 3 085 consumption points (PPE) with a total estimated volume (+/- 10%) 43 925.41 MWh, of which:
1) to premises and facilities (part 1 of the contract) - 29 487.10 MWh - a detailed list of PPE is attached as Annex 1a to the Terms of Reference;
2) for the purpose of road lighting (part 2 of the contract) - 14 438.31 MWh - a detailed list of PPE is attached as Annex 1b to the Terms of Reference.
The forecast electricity consumption indicated above is indicative and may differ from the amount of energy actually consumed during the contract period. Reducing or increasing the amount of energy consumed does not entail any consequences for the Ordering Party (recipients), except for the need to pay for the energy actually consumed at the rates specified in the contract.
1. Number of measuring systems accounting for consumed electricity 1 788 pcs.
2. A detailed description of the collection points (PPE) the Employer has included in Annex 1a to the ToR.
3. Estimated electricity consumption during the contract period (+/- 10%) 29 487.10 MWh, of which:
Zone I 13 990.66 MWh;
Zone II 10 113.73 MWh;
Zone III 5 382.71 MWh.
The above data is indicative. The contractor should take into account possible fluctuations in electricity consumption.
1. Number of measuring systems accounting for electricity consumed 1 297 pcs.
2. A detailed description of the collection points (PPE) has been placed by the Employer in Annex 1b to the ToR.
3. Estimated electricity consumption over the contract period (+/- 10%) 14 438.31 MWh, of which:
Zone I 13 249.18 MWh;
Zone II 1 189.13 MWh;
Zone III 0.00 MWh.
The above data is indicative. The contractor should take into account possible fluctuations in electricity consumption.