Main dimensions of dismantling/demolition work:
- Lifeguard's house with workshop extension approx. 790 m³
- Kabinengebäude ca. 4.500 m³
- Schwimmmeisterkabine ca. 480 m³
- Technical/pump house approx. 380 m³
- Bridge/footbridge over stream length approx. 5 m, width approx. 1.0 m
- various swimming pools total floor area approx. 2,200 m²
- Removal and disposal of polluted soils, approx. 6,300 m³
- Removal and disposal of surface sealing approx. 3,500 m²
- Dismantling and disposal of approx. 950 m² of asbestos-containing panels
The city of Memmingen, Stadtwerke Memmingen, intends to dismantle the existing outdoor swimming pool in Memmingen. In the course of the planned new building, a so-called combined pool (outdoor and indoor pool) is to be built.
The scope of this tender includes the work on the buildings:
Lifeguard's house with workshop extension (1 storey -
with partial basement), cabin building (2 storeys without basement), swimming master cabin (1 storey), technical / pump house (1 storey), bridge / jetty over the stream, Kneipp facility and trough, various swimming pools.
Removal of polluted soils for the following services:
Gutting and pollutant remediation, dismantling and excavation.
The construction site access is possible via Stadtbadallee 3 in 87700 Memmingen.
In the course of the planned dismantling of the outdoor pool, the existing buildings must be subjected to pollutant remediation before the buildings are demolished.
can.
The renovation area is located at Stadtbadallee 1 in Memmingen.
The renovation of the buildings includes the dismantling of the entire buildings. Subsequently, the soil exposed to pollutants is removed.
The outdoor swimming pool in Memmingen was built in the 1960s.
In principle, the pollutants (the following hazardous wastes are generated: asbestos, KMF, building materials containing PAHs and tar cork, waste wood) must always be removed before demolition. The existing pollutants can cause considerable damage to health and may only be processed by suitable companies with suitable, preventively examined and trained personnel with appropriate protective equipment, as well as suitable protection and safety measures
Become.
Scheduled schedule:
Start of work within 12 working days after receipt of the request, which is expected to be received in week 41/2022.
gutting work 1 week,
Pollutant remediation 3 weeks,
Superficial demolition 8 weeks,
Manufacture of sheet piling,
Underground demolition 6 weeks,
Excavation of polluted soils 6 weeks