Production of outdoor facilities according to
New construction of the children's and youth hospice.
The outdoor facilities around the new hospice building will be built in two sections, as
At present, the helipad is still located in the area of the construction site. As this
must be ready for operation at all times during construction work, as must the
ambulance route, can the outdoor facilities there only after it has been decommissioned
can be produced. This is expected to be the case from July 2023.
Construction of all outdoor facilities is planned for October 2023. Vegetative
Maintenance work is also another growing season until October 2024
to continue.
In the first construction phase, starting from July 2022, all outdoor facilities will be built north
the fire access road, the fire access road from the parking lot access to the central
terrace (“beak”) and the large parking lot in the eastern corner of the property
produced. The construction measures include, in particular, the production
- all paths and terraces in the vicinity of the hospice building
- car parking spaces and their access roads
- fire access to the large terrace
- the hospice courtyard with extensive dry stone walls and a staircase system
- a bicycle shelter
- the cladding and greening of the AWT tunnel
- the restoration of the escape route in the area of the AWT tunnel
- of meadows and plants
The relocation of the helipad is planned for June 2023, so that at the latest
The second construction phase can start from July 2023. This includes
manufacturing
- the rest of the fire access road
- all parking and connection routes
- and installation of all play equipment
- a log cabin with a fireplace
- a memorial site
- as well as extensive meadows and plants
After completion of planting work in autumn 2023, maintenance work is another year
to continue until autumn 2024.
The contractor must obtain information from the city of Bamberg about applicable
regulations, regulations, etc. and comply with them at all times.
Particular attention must be paid to cleanliness on the construction site. The construction site is open daily
to clean.
Demolition material, construction debris and construction site waste are in accordance with Bayer. Waste Management Act
dispose of properly and on your own responsibility at your own expense. Evidence of
Proper disposal must be presented to the client.
If nothing to the contrary is stated in the items, the termination and
Construction material is the property of the contractor and must be disposed of.
Your own construction waste must be removed and disposed of immediately.
If this is not done as requested by the site management, the
work carried out by third parties and the costs incurred
Deducted cleaning and disposal.
The safety regulations in accordance with the Construction Site Ordinance and SIGE Plan must be
take into account and comply with them.
The contractor reserves the right to take out construction insurance and this
pro rata to the companies involved in the final statement amounting to a maximum of 0.30% of the gross
Deduct the settlement amount.
The contractor is responsible for the costs of building electricity, construction water and sanitation
institutions amounting to 1.0% of the gross settlement total, this will be reflected in
deducted from the final account.
It should be noted that no corporate advertising is mounted on the hoarding or building
may be.
A building sign is created by the client, on which the respective company is
can contribute to a sign in terms of cost.
General building authority approvals,
provide test certificates or other necessary evidence and inform the client
to present approval.
In addition, the corresponding compliance specialist contractor declarations for
create and submit.
The notes in the preliminary remarks of the specifications must be observed and
must be observed.
Wage and material price sliding clause:
The unit prices to be offered are fixed prices until 31.10.2024. Wage increases are
to include this period.