The 4.5 Kampfmittelräumung TF 12 2023
-approx. 53,000 m² of explosive ordnance sounding on cleared forest area (root stubs are removed and including lateral free-cut or partially cleared areas in individual areas)
-Approx. 53,000 m² of surface inspection and recording of interfering bodies that influence sounding
-approx. 17,700 m² flat removal of topsoil strongly interspersed with interfering bodies (pieces of barbed wire, iron residues, combat equipment), removal of interfering bodies, storage of soil laterally on rents
-approx. 507 hours of opening, clearing and closing of any suspected points, depth up to 2.5 m, uneven terrain
-approx. 1960 m³ excavated soil for exposing and removing pipes
-Explosive ordnance search and clearance in 2 different parts of rhR Weil Breisach III in two separate periods (spring 2023 and winter/spring 2023/2024)