The contract concerns building site partitions, alterations to address changed escape conditions, noise measures and some new installations on the facade.
The contract concerns building site partitions, alterations to address changed escape conditions, noise measures and some new installations on the facade.
Building site partitions must be established between hospitals that are in operation and objects that will be demolished under other contracts. The building site separations will be in the form of temporary walls that comply with the relevant requirements for HSE, noise and climate separation. In connection with this, the technology that supplies the demolition objects must also be disconnected or altered so that demolition can be carried out independently of hospital operations. The relevant demolition objects for which preparations are being made are D1 Descent shaft and service pavilion, B1 tower and B1 canteen pavilion.
In area E1 south, minor remodelling will be carried out to comply with the changed escape conditions. The work will mainly be carried out in a corridor and in adjacent rooms. A new escape route to the west will be established in the E1 vestibule. A new porch will also be established here. The existing entrance and east-facing porch will be dismantled when the new entrance is put into operation.
To shield the existing hospital from noise from the building and construction work, goods windows will be installed in a large proportion of the rooms in buildings B, D and E that border the current vestibule.
After the demolition of the pavilions and towers has been completed (carried out by another company), measures will be carried out under Contract 2050 in the demolition stage. Measures will be temporary or permanent climate barriers in the form of glass façades, cladding or temporary climate walls.
The contract has a number of interfaces with Contract 2912 (demolition of pavilions, stair towers, etc. in the current vestibule), and work must be coordinated with this contract.
The contractor must take into account extensive meeting activities prior to execution, obligations to notify and signage requirements. See 3.4 Meeting structure, 6.3 Considerations for hospitals in operation and 8.1.2 Building fences and signage.