New construction of a four-school integrated comprehensive school - window and glazing work.
Execution of the window and glazing work for the new construction of a four-level integrated comprehensive school with auditorium and 2-field sports hall and official residence.
- BGF approx. 14 500 m²,
- BRI approx. 62 450 m³.
The works essentially include:
- approx. 1,090 m² of wood-aluminum window elements, with and without fire protection requirements,
- about 350 running meters window sills,
- approx. 1,980 m² wooden-aluminum-post-and-beam facades, with and without fire protection requirements,
- 4 windscreen elements without fire protection requirements, integrated in the mullion-transom façade, as clad steel construction, with wood-aluminum exterior facade and wooden interior façade,
- approx. 14 aluminum exterior door elements, with and without fire protection requirements,
- approx. 1,600 m² of sun protection, as aluminum slat external venetian blinds, rail-guided on window elements and post-and-beam facades,
- approx. 90 m² sun protection, as aluminum slat external venetian blinds, cable-led on post-and-rail facades of the inner court of the school.