Ventilation installation work | Tenderlake

Ventilation installation work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
05 June 2023
Closing Date:
28 June 2023
Location(s):
DE11A Schwäbisch Hall (DE Germany/DEUTSCHLAND)
Description:
Ventilation systems

New construction of the Schwäbisch Hall correctional facility

Ventilation systems

- Pos. 01 consisting of 2 ventilation systems for the station building with heat recovery, heating, cooling and cooling

Filters with 25,000m3/h each

- Item 02 consisting of 1 ventilation system for occupational therapy

- Pos. 03 1 Kitchen ventilation unit with heat recovery, heating and filtering with approx. 7,000m3/h

- Approx. 400 fire dampers 230V for pos. 01

- Approx. 40 fire dampers 230V for pos. 02

- Approx. 20 fire dampers 230V for pos. 03

- Ca. 8 Entrauchungsklappen

- Ca. 400 Konstantvolumenstromregler

- Ca. 300 Drallluftauslässe

- Approx. 180 poppet valves supply and exhaust air

- Ca. 400 Telefonieschalldämpfer

- Ca. 50 Kulissenschalldämpfer

- Approx. 5800m2 ventilation duct incl. insulation

- Ca. 2400m Wickelfalzrohr

- Ventilation ceiling for the kitchen area

- Approx. 10 EDP split air conditioners

- Lüftungsfunktionsdecke

Download full details as .pdf
The Buyer:
Klinikum am Weissenhof Zentrum für Psychiatrie Weinsberg, AöR
CPV Code(s):
45331210 - Ventilation installation work