The contract shall mainly involve the establishment of the perimeter with masts for surveillance, as well as a road suitable for vehicles on the inside of the perimeter.
The perimeter:
— approx. 9 km demolition and disposable of the existing fence, h = 2,5 m + 1 m,
— approx. 7,5 km new road that is suitable for vehicles, simple standard,
— approx. 10 km fence, h = 4 m,
— approx. 140 masts, h = 4-6 m,
— approx. 11 km cable ditch with conduits,
— approx. 14 km forest/thicket clearance over a width of 5 m on the outside of the new and existing perimeter,
— 30 gates of various types,
— option for a new inner perimeter, approx. 3 km fence, h = 2,5 m.