carpentry work
It is the provision of carpentry work for the
Expansion of the primary school Breloh incl. the renovation
existing building.
The execution includes the following:
new building:
- Production of approx. 230 m² wall cladding made of wood including all
required work
- Delivery and installation of 2 equipment room doors and 5 wooden interior doors incl.
all necessary work
- Production of wall cladding in the area of the cafeteria outlet including all
required work
- Production of approx. 28 m² side cladding of parapets including all
required work
- Production of approx. 165 m of window sills for interior, including all
required work
- Delivery and installation of 6 toilet partitions incl.
all necessary work
- Delivery and installation of, among other things, seating elements, cloakrooms and picture screens including all necessary work
Old house:
- Delivery and installation of, among other things, a kitchenette and worktops in the PC room including all necessary work
- Delivery and installation of 2 toilet partitions incl.
all necessary work