This contract defines the conditions under which the CEA entrusts the Contractor, which accepts, with the manufacturing study, construction, inspections and delivery of 80 (eighty) G11 poles for cryomodules within the framework of the PIP-II project
The services of the lump sum part entrusted to the Account Holder are divided into three phases described as follows:
Phase 1: a manufacturing study phase. This phase will start from the kick-off meeting. The manufacturing study will be based on the drawings communicated by the CEA validated at the "for realization" stage,
Phase 2: a manufacturing phase of one (1) set of 8 (eight) pre-production G11 poles (PG0). For this phase, the CEA reserves the right to make some minor changes to the plans submitted during phase 1. The Account Holder undertakes to take these changes into account without financial consequences.
Phase 3: a manufacturing phase of nine (9) sets of 8 series G11 poles (PG1 to PG9), i.e. 72 G11 posts.
For this phase, the CEA reserves the right to make changes in order to take into account the results of phase 2. The Account Holder undertakes to take these changes into account.