The publication includes the performance of closing fire safety:
— Start of service (W+M planning, ordering, production): 31.1.2022,
— start of work on the construction site: 28.2.2022,
— Completion including all construction work: 9.9.2022.
Core quantities:
— 106 pcs. ELT mortar bulkhead reinforced concrete S90 0.01 m
— 47 pcs. ELT mineral fiber bulkhead reinforced concrete S90 diameter up to 250 mm,
— 29 pcs. ELT mineral fiber bulkhead reinforced concrete 0.02 m
— 10 pieces ELT mineral fibre bulkhead masonry S90 diameter up to 100 mm,
— 10 units ELT mineral fibre bulkhead drywall diameter up to 100 mm,
— 10 pieces of ELT fire protection stone,
— 282 pcs. HLS closure of openings up to 2 000 cm
— 101 pcs. HLS closure of openings from 2 000 cm
— 6 pcs. HLS closure of openings from 5 000 cm
— approx. 22 m