The subject of the contract is the extension of the national road No. 65 on the section Olecko - Gąski from km 43+289 to km 49+150
1. The subject of the contract is the extension of the national road No. 65 on the section Olecko - Gąski from km 43+289 to km 49+150.
This task includes:
– construction of a new roadway structure with a permissible load of 115 kN / axle with a width of 8.0 m,
– correction of vertical and horizontal arches
– construction/reconstruction of culverts
– reconstruction of the bridge structure into a culvert
– construction of pedestrian routes
– extension of intersections
– construction of bus bays
– construction of vehicle weighing points
– construction of road lighting
– felling/planting trees, shrubs
– road drainage
– construction of a technological channel
– construction of an acoustic screen
– construction/reconstruction of exits
– execution of BRD elements
– reconstruction of the existing technical infrastructure colliding with the planned road demolition of buildings
– construction of environmental protection equipment and facilities
2. Total estimated order of magnitude of contract value: above EUR 5 382 000 and below EUR 20 000 000.
3. The contracting authority requires that the works, together with obtaining the occupancy permit, be completed within no more than 16 months from the date of conclusion of the contract. Winter periods, i.e. from 16 December to 15 March, counted as three months, are not included in the implementation time.