Sandefjord Airport AS (SLH) shall replace and renovate the ventilation plants in the southern part of the terminal at Torp Sandefjord Airport. A ventilation plant shall be replaced due to the generator's poor condition. A channel system shall be reconstructed for adaptation to the current design and requirement.
The following main measures shall be carried out:
— The current ventilation plant 36.07 serves the departure /arrival hall and various service/business areas and offices in the south wing's ground and first floors. The generator is installed on the south wing's roof for the departure /arrival hall. The capacity of the generator is 30 000 m
— Generator 36.09 with a capacity of 16 000 m
— The channel systems, valves, etc. shall be adapted to the new design and the current requirements.
— The air flow rate in the generators shall be adapted to requirements and controlled by the air's CO 2 content and the temperature in the involved zones.