Trenches various networks / sewerage: approx. 770m² Pipes and various networks: approx. 1670 ml Manholes and printing chambers: 13pc Surfaces of concrete pavers of different heights: approx. 820 m² Natural stone stairs and concrete blocks: 4 rooms Natural stone paving: approx. 92 m² Drainage: approx. 70 ml Concrete border: approx. 80 ml The works are awarded in blocks at unit prices. The duration of benefits is 135 working days starting in January 2024
Trenches various networks / sewerage: approx. 770m² Pipes and various networks: approx. 1670 ml Manholes and printing chambers: 13pc Surfaces of concrete pavers of different heights: approx. 820 m² Natural stone stairs and concrete blocks: 4 rooms Natural stone paving: approx. 92 m² Drainage: approx. 70 ml Concrete border: approx. 80 ml The works are awarded in blocks at unit prices. The duration of benefits is 135 working days starting in January 2024