sanitary equipment
Plumbing work with the following approx. quantities:
300 m sewer pipe (mineral reinforced PP pipes)
140 m sewer pipe (HT pipe)
20 m sewer pipe (KML pipe)
100 m condensate drainage (PVC pipe)
30 m internal rainwater drainage (PE-HD pipe)
650 m copper pipe
600 m stainless steel pipe
10 pcs electronically controlled instantaneous water heaters
125 pcs Fire protection bushings for copper and stainless steel pipes
40 pcs fire protection sleeves for sewage pipes
7 St Gebäudeeinführungen
38 St WC
4 St Beh.-WC
25 pcs washbasins
4 pcs Beh. washbasin
2 x draining sinks
13 pcs urinals
3 St frostsichere Außenzapfstellen
1 pc extinguishing water supply ("dry")
1 St Entnahmearmatur
1 x rainwater use system
1 pc chlorine dioxide measuring and control system
1 St Doppelenthärtungsanlage
1 St Frequenzgesteuerte Umkehrosmoseanlage
1 St Betriebswasserzentrale
105 pcs core drilling
Provision of planning services: work and assembly planning
Ausführungsbeginn: 15.02.2024 Start Montageplanung