Construction works involving the construction of a logging route.
Scope of planned works:
- development of the tourist / skidding trail on the length of approx. 365 m and width 2.5 m,
- development of the route by means of waterworks, 10 pieces,
- development of the route with wooden thresholds 8 pcs.
A detailed description of the construction works constituting the subject of the contract is defined in the project documentation including:
- Building design - Annex No. 11 to the ToR
- Detailed design - Annex No. 12 to the Terms of Reference
- Bill of quantities - Annex No. 10 to the Terms of Reference
- Detailed Technical Specifications for the Execution and Acceptance of Works - Annexes No. 9 to the ToR.
The contracting authority requires the preparation of as-built geodetic documentation.
Scope of planned works:
- development of the tourist / skidding trail on the length of approx. 365 m and width 2.5 m,
- development of the route by means of waterworks, 10 pieces,
- development of the route with wooden thresholds 8 pcs.
The contracting authority requires the preparation of as-built geodetic documentation.