Correction of defects on the transition piece of all TWB2 wind turbines:
SOW 1: Exchange of 17 ventilator fan drives on the Transition Pieces (TP);
SOW 2: Mechanical retrofits on handrails, swinggate stoppers, as well as WTG tower door bumpers and holders on main access platforms of 31 TPs;
SOW 3:Testing and re-setting of Draeger H2 / Cl sensors on 31 TPs.
Preparation phase
— preparation and provision of risk assessment and method statement;
— preparation and provision of task plan of offshore operation;
— preparation and provision of project time schedule;
— preparation and provision of technical equipment and material list;
— preparation and participation in kick off meeting.
Execution phase
— provision of a suitable crew transfer vessel by contractor;
— organisation of accommodation by contractor;
— daily reporting;
— execution of offshore operation (SOW1, SOW2 and SOW3).
Post-processing phase:
— preparation and provision of final documentation;
— preparation and participation in lessons learnt meeting.