The item of the Order is divided into six parts: Part No 1 - delivery of building materials: concrete cube; Part No 2 - delivery of building materials: curb, edging, openwork slab, resistor; Part No 3 - delivery of building materials: cement-sand subplet, freight concrete;
Part No. 4 - delivery of building materials: stone aggregate, aggregate. Part No. 5 - delivery of building materials: sand. Part No. 6 - delivery of building materials: YOMB.The object of the contract is the recurring supply of the Ordering Party with building materials consisting of their delivery and unloading in places indicated in the orders awarded by the Contracting Authority. The Contracting Authority reserves the possibility of receiving by his own transport — it relates to parts 1, 3, 4, 5. The loading is on the Supplier's side. The order will be implemented from 01.01.2022 until 31.12.2022 or the quota limit is exhausted.
delivery of building materials: concrete cube.The Contractor is obliged to deliver and unload the object of the contract at his own expense to the places indicated by the Ordering Party, among the following: the headquarters of the Ordering Party - 78 Gdańska Street in Władysławowo, the sites of the building blocks carried out by the Ordering Party and located in the Wladysławowo Municipality, sites of building houses implemented within the borders of the Pomeranian Voivodeship. The Contracting Authority reserves the possibility to receive its own transport of building materials — concrete cube (part no. 1). Then the loading lies on the Supplier's side. The Ordering Party will each time anticipate the need for a particular construction by sending an order to the Provider in order to prepare for the delivery of a given quantity of building materials. The quantity of materials indicated in the order must be prepared for delivery within 7 days from the date of sending the order by email. Delivery of materials to the places indicated in the order will be made within 2 days of the notification by telephone or e-mail by persons authorized by the Contracting Authority. As a rule, the delivery of a given order will be carried out with full transports. The Contracting Authority stipulates that the last delivery batch of the order in question may be carried out as delivery with incomplete transport. Accordingly, the supplier will not demand additional remuneration from the Ordering Party related to the delivery of the cube with incomplete transport. The offer price for the supply of building materials should include; all costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period.Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier.
The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material. The quantities of building materials listed above are the estimate, the actual quantities of the building material ordered may be smaller. In this case, the Suppliers do not serve for this claim. Pallets will be returned to the Supplier at the request of the Ordering Party within a period of not less than 30 days and not more than 120 days from the date of delivery of the pallet in question, and their price does not fall into the cost of the materials (the Supplier will not charge the Ordering Party for pallets). The cost of using pallets by the Ordering Party must be calculated in the price of the material. If the Ordering Party exceeds a time limit of 120 days for the return of pallets, the Supplier will charge the Ordering Party for the cost of pallets at the unit price specified in the Supplier's offer. Price per 1 pallet is one of the criteria for assessing bids and the Supplier will declare the price per 1 pallet in point 2B of the Offer Form.
delivery of building materials: curb, edging, openwork plate, resistance.The Contractor is obliged to deliver and unload the object of the contract at his own expense to the places indicated by the Ordering Party, among the following: the headquarters of the Ordering Party - 78 Gdańska Street in Władysławowo, the sites of the building blocks carried out by the Ordering Party and located in the Wladysławowo Municipality, sites of building houses implemented within the borders of the Pomeranian Voivodeship. The Contracting Authority reserves the possibility to receive its own transport of building materials — concrete cube (part no. 1). Then the loading lies on the Supplier's side. The Ordering Party will each time anticipate the need for a particular construction by sending an order to the Provider in order to prepare for the delivery of a given quantity of building materials. The quantity of materials indicated in the order must be prepared for delivery within 7 days from the date of sending the order by email. Delivery of materials to the places indicated in the order will be made within 2 days of the notification by telephone or e-mail by persons authorized by the Contracting Authority. As a rule, the delivery of a given order will be carried out with full transports. The Contracting Authority stipulates that the last delivery batch of the order in question may be carried out as delivery with incomplete transport. Accordingly, the supplier will not demand additional remuneration from the Ordering Party related to the delivery of the cube with incomplete transport. The offer price for the supply of building materials should include; all costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period.Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier.
The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material. The quantities of building materials listed above are the estimate, the actual quantities of the building material ordered may be smaller. In this case, the Suppliers do not serve for this claim. Pallets will be returned to the Supplier at the request of the Ordering Party within a period of not less than 30 days and not more than 120 days from the date of delivery of the pallet in question, and their price does not fall into the cost of the materials (the Supplier will not charge the Ordering Party for pallets). The cost of using pallets by the Ordering Party must be calculated in the price of the material. If the Ordering Party exceeds a time limit of 120 days for the return of pallets, the Supplier will charge the Ordering Party for the cost of pallets at the unit price specified in the Supplier's offer. Price per 1 pallet is one of the criteria for assessing bids and the Supplier will declare the price per 1 pallet in point 2B of the Offer Form.
delivery of building materials:cement-sand subbacklash, freight concrete.A. The Contractor shall supply and unload the object of the contract at his own expense to the places indicated by the Contracting Authority, among the following:
- headquarters of Ordering - 78 Gdańska Street in Władysławów,
- the sites of construction houses carried out by the Ordering Party and located in
The Municipality of Władysławowo,
- sites of building houses implemented within the borders of the Pomeranian Voivodeship.
The Contracting Authority reserves the possibility of receiving its own transport. Then the loading lies on the Supplier's side.
B. Delivery of materials to the places indicated in the order will be carried out within... hours of the notification by telephone or e-mail by persons authorized by the Contracting Authority. Delivery date from the application is one of the criteria for assessing tenders and the Contractor will declare the delivery period in point 2C of the Offer Form.
C. The offer price for the supply of building materials should include; all costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period, shall apply to items with transport. In items without transport, the offer price for the supply of building materials should include; any costs, including landing at the place of delivery, and shall not change throughout the delivery period.
D. Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier. The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material.
E. The quantities of building materials listed above represent the estimate, the actual quantities of the building material ordered may be smaller.
In this case, the Suppliers do not serve for this claim.
G. The Contracting Authority stipulates that the supply of a given order in terms of cement-sand and concrete fuels can be carried out as a supply with incomplete transport, i.e. the minimum supply in question may be 1.5 m3 of concrete or cement-sand backfilling. Therefore, the supplier will not demand additional remuneration from the Contracting Authority related to the supply of concrete or incomplete transport.
H. The warranty period will be 36 months from the date of delivery.
delivery of building materials: stone aggregate, aggregate.A. The Contractor shall supply and unload the object of the contract at his own expense to the places indicated by the Contracting Authority, among the following:
- headquarters of Ordering - 78 Gdańska Street in Władysławów,
- the sites of construction houses carried out by the Ordering Party and located in
The Municipality of Władysławowo,
- sites of building houses implemented within the borders of the Pomeranian Voivodeship.
The Contracting Authority reserves the possibility of receiving its own transport. Then the loading lies on the Supplier's side.
B. Delivery of materials to the places indicated in the order will be carried out within... hours of the notification by telephone or e-mail by persons authorized by the Contracting Authority. Delivery date from the application is one of the criteria for assessing tenders and the Contractor will declare the delivery period in point 2C of the Offer Form.
C. The offer price for the supply of building materials should include; all costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period, shall apply to items with transport. In items without transport, the offer price for the supply of building materials should include; any costs, including landing at the place of delivery, and shall not change throughout the delivery period.
D. Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier. The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material.
E. The quantities of building materials listed above represent the estimate, the actual quantities of the building material ordered may be smaller.
In this case, the Suppliers do not serve for this claim.
G. The Contracting Authority stipulates that the supply of a given order in terms of cement-sand and concrete fuels can be carried out as a supply with incomplete transport, i.e. the minimum supply in question may be 1.5 m3 of concrete or cement-sand backfilling. Therefore, the supplier will not demand additional remuneration from the Contracting Authority related to the supply of concrete or incomplete transport.
H. The warranty period will be 36 months from the date of delivery.
delivery of building materials: sand.A. The Contractor shall supply and unload the object of the contract at his own expense to the places indicated by the Contracting Authority, among the following:
- headquarters of Ordering - 78 Gdańska Street in Władysławów,
- the sites of construction houses carried out by the Ordering Party and located in
The Municipality of Władysławowo,
- sites of building houses implemented within the borders of the Pomeranian Voivodeship.
The Contracting Authority reserves the possibility of receiving its own transport. Then the loading lies on the Supplier's side.
B. Delivery of materials to the places indicated in the order will be carried out within... hours of the notification by telephone or e-mail by persons authorized by the Contracting Authority. Delivery date from the application is one of the criteria for assessing tenders and the Contractor will declare the delivery period in point 2C of the Offer Form.
C. The offer price for the supply of building materials should include; all costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period, shall apply to items with transport. In items without transport, the offer price for the supply of building materials should include; any costs, including landing at the place of delivery, and shall not change throughout the delivery period.
D. Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier. The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material.
E. The quantities of building materials listed above represent the estimate, the actual quantities of the building material ordered may be smaller.
In this case, the Suppliers do not serve for this claim.
G. The Contracting Authority stipulates that the supply of a given order in terms of cement-sand and concrete fuels can be carried out as a supply with incomplete transport, i.e. the minimum supply in question may be 1.5 m3 of concrete or cement-sand backfilling. Therefore, the supplier will not demand additional remuneration from the Contracting Authority related to the supply of concrete or incomplete transport.
H. The warranty period will be 36 months from the date of delivery.
delivery of building materials: YOMB board.A. The Contractor shall supply and unload the object of the contract at his own expense to the places indicated by the Contracting Authority, among the following:
- headquarters of Ordering - 78 Gdańska Street in Władysławów,
- the sites of construction houses carried out by the Ordering Party and located in the Municipality of Władysławowo,
- sites of building houses implemented within the borders of the Pomeranian Voivodeship.
B. The Contracting Authority shall each time anticipate the need for a particular construction by sending an order to the Provider in order to prepare for delivery of a given amount of YOMB plates. The quantity of materials indicated in the order must be prepared for delivery within 7 days from the date of sending the order by email. Delivery of materials to the places indicated in the order will be made within 2 days of the notification by telephone or e-mail by persons authorized by the Contracting Authority. As a rule, the delivery of a given order will be carried out with full transports. The Contracting Authority stipulates that the last delivery batch of the order in question may be carried out as delivery with incomplete transport.
Accordingly, the supplier will not demand additional remuneration from the Ordering Party related to the supply of YOMB discs with incomplete transport.
C. The offer price for the supply of building materials should include; any costs, including transport and landing at the place of delivery, and shall not change throughout the delivery period.
D. Any delivery must be confirmed by the person appointed by the Contracting Authority on the WZ document issued by the Supplier.
The original WZ document will form the basis for the qualitative and quantitative reception of the ordered batch of material.
E. The quantities of building materials listed above represent the estimate, the actual quantities of the building material ordered may be smaller.
In this case, the Suppliers do not serve for this claim.
The top surface of YOMB plates must be obliterated smoothly.