I. Object of the contract:
Successive collection and use of RDF alternative fuel with code 19-12-10 until 31.7.2020 with the possibility of submitting partial offers according to Estimated quantity for lots from 1 to 5.
In MZKZOK, the production of alternative fuel (RDF) uses flammable fractions of waste free of ferrous and non-ferrous metals and PVC. Alternative fuel (RDF: 19 12 10) with the possibility of submitting partial bids.
Part 1
- ground into fractions, grinding to 30 mm,
- calorific value up to 18,000 kJ / kg
- chlorine content up to 0.7%,
- humidity up to 15%.
Fuel weight 1 600 Mg.
The Employer requires that the Contractor has at least two trucks with walking floor bodies with a loading capacity of 90 m
Part 2
- ground into fractions, grinding to 30 mm,
- calorific value from 18,000 to 20,000 kJ / kg
- chlorine content up to 0.7%,
- humidity up to 15%.
Fuel weight 1 100 Mg.
The Employer requires that the Contractor has at least two trucks with walking floor bodies with a loading capacity of 90 m
Part 3
- ground into fractions, grinding to 30 mm,
- calorific value above 20,000 kJ / kg
- chlorine content up to 0.7%,
- humidity up to 15%.
Fuel weight 800 Mg.
The Employer requires that the Contractor has at least two trucks with walking floor bodies with a loading capacity of 90 m
Part 4
- ground into fractions, grinding to 30 mm,
- calorific value up to 19,000 kJ / kg
- chlorine content up to 0.7%,
- humidity up to 20%.
Fuel weight 1 600 Mg.
The Employer requires that the Contractor has at least two trucks with walking floor bodies with a loading capacity of 90 m3 for each part of the task. Alternative fuel collection will take place from Monday to Friday from 6:00 to 22:00. The customer will ensure loading. Each vehicle must be equipped with an efficient, operational and recording the route of the vehicle on a current basis gps system.
Part of the 5th
- ground into fractions, grinding to 30 mm,
- calorific value above 19,000 kJ / kg
- chlorine content up to 0.7%,
- humidity up to 20%.
Fuel weight 1 400 Mg.
The Employer requires that the Contractor has at least two trucks with walking floor bodies with a loading capacity of 90 m