Construction of a carpooling car park near motorway interchange n° 29 (ASF network): preparatory work, earthworks, sanitation, pavements, curbs, pavements, signage, various networks, equipment, etc. (non-exhaustive list of works) on the Provence Auvergne Rhône Alpes Regional Directorate (DRE PARA)
(Quantities given for information purposes only)
Asphalt demolition: 1232 m²
- Sidewalk demolition:
- Curb demolition: 215 ml
- Excavated earthworks and approved landfill disposal: 2,747 m3
- Compaction of the bottom and supply and implementation of geotextile in class 5: 3040 m²
- Supply and implementation of GNT 0/63 for base layer: 1218 m²
- Supply and installation of PP SN16 pipes with a diameter of 350: 105 ml
- Supply and installation of D800 manholes, incl. cast iron stamp: 7 u
- Supply and installation of 75x30 grid manholes, including cast iron pad: 8 u
- Supply and installation of a control manhole with overflow at the outlet of the EP basin, including cast iron grate: 1 u
- Supply and installation of 63mm diameter sleeves including connection and installation beds: 290 ml
- Supply and installation of light tower: 11 u
- Supply and installation of lighting control cabinet: 1 u
- Supply and implementation of BBSG 0/10 for surface course (thickness 6cm): 219 T
- Supply and installation of an impregnation layer: 1515 m²
- 8cm thick draining paving stones including square demarcation line: 1187 m²
- Supply and installation of T2 edging including low edging and glued edging: 575 ml
- Horizontal signage, solid or dashed lines: 118 ml
- Vertical Police Signage: 29 u
- Directional signal crane: 48 m²
- Supply and installation of 2m high fence with rigid panels: 335 ml
- Supply and installation of a waiting shelter: 1 u
- Supply and installation of swivel jigs: 3 u
- Creation of a wetland: 1 u
- Planting of 18/20 tall stem trees: 32 u