Screed work 1_BA
Brief description of the measure:
On the site of IGS Lindenfeld, a 3-storey extension for a primary school is to be built next to the existing main building. The construction project will be carried out in 2 construction phases. The service described here concerns the 1st construction phase.
Further descriptions: see bill of quantities
Execution times:
Technical clarification: within 4 weeks after placing the order
Screed work: 08.01. - 26.01.2024
Needling and resinification: 11.03. - 15.03.2024
Main positions
Floor levelling mass d = 30mm 700 sqm,
Floor levelling mass d = 20mm 1.420 sqm, MW-TSD 30mm 2.120 sqm
Cement screed d=65mm 2.120qm