Dachabdichtungsarbeiten
approx. 2620 m2 roof waterproofing with thermal insulation
ca. 2400 m2 Retention
approx. 525 m wall and edge finishes
ca. 8 Dachabläufe
ca. 12 Notabläufe
approx. 72 m downspouts
approx. 1980 m2 green roof
Intermediate deadlines for execution:
Start of execution:
Building 6/7: 1st week 2024
Building 41: no earlier than week 11, 2024
House 40: no earlier than week 40 2024
Execution end:
House 6/7: within 40 working days
House 41: within 60 working days
House 40: within 60 working days
after the aforementioned deadline for the commencement of execution