Masonry, concrete, screed and plaster work in the new part Bt. N as part of the core castle
S-394 extended body shell BT N
Tenders have been issued for masonry, concrete, screed and plaster work in the new part BT N as part of the core castle.
Plaster works:
- 3200 m² lime plaster on walls
- 820 m" lime plaster on ceilings
- 180 m² thermal insulation plaster on walls
Bricklayer:
- Make 30 m² KS masonry
- Modification of 15 door openings
- Making 2 new doorways in masonry
Concrete:
- Making a ceiling opening
- Making a doorway in reinforced concrete wall
screed
- 1,350 m² screed as heating-cement screed
Construction of the trade is scheduled to begin in week 10 2024. The construction process will be staggered according to components, completion by 30 week 2025.
Staggered journeys are required to provide services