Description:
daf_2023_001022 - vALDAHON (25) - 13th RG - renovation bivouac island 1

valdahon (25) - 13th RG - renovation bivouac islet 1

Lot 1: Asbestos removal - demolition

This lot includes:- asbestos removal from existing buildings;- removal of frameworks/roofing/metal cladding/interior equipment from existing buildings

Lot 2: Roads and Highways

This lot includes in particular:- the stripping of the area;- the construction of the platform;- the installation of the networks (EP, CFO ducts, CFA ducts, AEP);- the construction of the asphalt;- the installation of the curbs and gutters;- the construction of the sidewalks

Lot 3: Structural work

This lot includes:- the construction of the foundations of the buildings;- the construction of the paving and the masonry structure of the new buildings;- the realization of the slabs for the placement of the tents;- the realization of the masonry walls for the buildings to be rehabilitated;- the realization of the screeds;- the installation of the interior coatings on the walls and floor (resin and plaster)

lot 4 : Facades -ITE

This lot includes in particular:- the installation of insulation for the exterior on the facades and basement of the new buildings;- the construction of the cladding for the new buildings

Lot 5: Frame - roof

This lot includes:- the construction of the framework for the new buildings and buildings 764 and 765;- the treatment of the existing framework for building 486;- the installation of a metal roof for the rehabilitated buildings;- the installation of insulation on the roof for the new buildings;- the installation of a metal roof after insulation on the new buildings

Lot 6 : Joinery

This lot includes in particular:- the supply and installation of all the project's frames (windows and doors)

lot 7 : CVC

This lot includes in particular (for new buildings only):- the installation of heat pumps (interior and exterior modules);- the installation of floor insulation;- the installation of underfloor heating;- the installation of a ventilation system in each building;- the installation of ventilation ducts and vents in each building;- the adaptation of air inlets and outlets on the façade and roof

lot 8: Electricity

This lot includes:- the installation of an Hv/LV transformer;- the pulling of all the electrical cables from the substation to the equipment;- the installation of electrical panels;- the installation of all the electrical equipment (lights, switch, socket, etc.);- the installation of electrical boxes for the tents;- the electrical renovation of the rehabilitated buildings

Download full details as .pdf
The Buyer:
esid de Metz
CPV Code(s):
45000000 - Construction work
45110000 - Building demolition and wrecking work and earthmoving work
45112500 - Earthmoving work