Construction of a wheelchair accessible entrance ramp
The performance for all trades essentially includes:
a) Preparatory actions
- Set up construction site
- coordination with AG
- Design planning in such a way that welding on site is not necessary
b) single foundation
- earthworks in manhole
- produce isolated foundations from reinforced concrete
c) fabrication steel structure
- Approval for the production of the steel structure by the AG after completion of the isolated foundations
- In the meantime, the lawn area under the entrance ramp to be created is concreted by the AG.
d) assembly
- Deliver steel structure and assemble on site
e) path lighting
- supply and mount path lighting in the form of LED strips along the entrance ramp including cabling and power supply
- the electrical connection is done by a third party on the part of AG.
f) crampons
- Deliver and install exit aid inside in front of the outer wall.
g) decollation work
- construction site equipment