This contract is a works contract.
The consists of:
1) Place a negative feeder between Paliseul and Bertrix on both tracks;
2) Place a negative feeder between Bertrix and Libramont;
3) Electrify line 162/1 and connections to the connection.
This contract includes:
additional execution studies on the basis of picket projects, cross profiles, concrete and pendulum notebook submitted by Infrabel;
supplies except materials made available by Infrabel;
excavations, concreting of massifs and evacuation of excavated material;
the installation of catenary poles and supports;
the installation of catenaries;
the removal of old supports.
This contract is a works contract.
The consists of:
1) Place a negative feeder between Paliseul and Bertrix on both tracks;
2) Place a negative feeder between Bertrix and Libramont;
3) Electrify line 162/1 and connections to the connection.
This contract includes:
additional execution studies on the basis of picket projects, cross profiles, concrete and pendulum notebook submitted by Infrabel;
supplies except materials made available by Infrabel;
excavations, concreting of massifs and evacuation of excavated material;
the installation of catenary poles and supports;
the installation of catenaries;
the removal of old supports.