L96 OD Milow, road construction
Clearing approx. 80 rootstocks
ca. 14.250 m² Fahrbahnaufbruch, Asphalt VWk A
ca. 500 t Fahrbahnaufbruch, Asphalt VWk C
approx. 420 t road demolition, asphalt f. Waste
approx. 8.470 m² Fahrbahnaufbruch, Natursteinpflaster
Accommodate approx. 2,400 m² of curbs
Approx. 6,010 m² of pavement pavement
approx. 1,610 m³ of topsoil removed and recycled
approx. 1,050 m³ of topsoil supply and cover
Loosen and recycle approx. 3,430 m³ of soil
Supplying and installing approx. 1,570 m³ of soil
approx. 17,945 m² installation of chipped mastic asphalt SMA 11 S, 4 cm thick
approx. 970 m² pavement of structural asphalt MA 11 S, 4 cm thick
approx. 550 m² installation of asphalt truss AC 16 BS, 6 cm thick
approx. 550 m² installation of asphalt base course AC 22 TS, 10 cm thick
approx. 18,355 m² paving asphalt base course AC 22 TS, 12 cm thick
approx. 4,010 m Constructing a drainage channel from large pavement
approx. 8,820 m² concrete block paving 8 cm
approx. 2,980 m² concrete block paving 10 cm
approx. 220 m² Making tactile concrete slabs 8 cm
Produce approx. 240 m² of natural stone paving
approx. 9,490 m³ paving ballast base course 0/32
approx. 6,770 m of granite shelves
approx. 8,090 m of concrete curbs/curbstones
Laying approx. 1,970 m of plastic pipeline DN 200-400
approx. 200 St street drains with connecting pipe DN 150
approx. 55 pcs Install precast shafts DU 1000
approx. 4 pcs make infiltration basin
approx. 38 hours Moving and reinstalling street lighting
approx. 30 m angle retaining wall H = 10-65cm with tubular steel railing h = 1.30m