Sewer construction work

Contract Value:
-
Notice Type:
Contract award notice – utilities
Published Date:
09 January 2023
Closing Date:
Location(s):
IE IRELAND
Description:
Athlone Main Drainage Contract No. 2 – Networks Design and Build Contract

Irish Water plan to undertake the construction of a new sewerage collection

network in Athlone including gravity sewers, 2 No. new pumping stations and 2 No. new storm tanks and rising main. The project will convey flows from Athlone to the

Athlone WwTP.

Irish Water is currently advancing the Athlone Main Drainage Contract No. 2 – Networks, comprising the construction of a new main lift pumping station, removal of storm overflows, new foul sewers, decommissioning of existing pumping stations and new large diameter trenchless pipeline (tunnel) sewers.

The Contract has been procured under a Negotiated Procedure and the form of contract is Design-Build-Operate.

The scope of the requirements to be provided as part of this project & contract include (but are not limited to) the design, construction, testing and commissioning of the following works at various sub-catchments:

 Design and construction of a new foul and storm water pumping station, control building, 4,100m3 storm water storage and associated ancillaries at Golden Island Pumping Station;

 Design and construction of a new foul and storm water pumping station, 110m3 storm water storage and associated ancillaries at Coosan West Pumping Station;

 Design and installation of various gravity sewers and rising mains (c.3km), using open cut and trenchless technology methods, meeting the requirements of the Scope, through public roads, and public and private lands;

 Design and installation of all required pipework and other ancillary works within the proposed Golden Island Pumping Station Site and proposed Coosan West Pumping Station Site;

 Decommissioning of 6 No. SWOs and upgrade of 1 No. SWO meeting the requirements of the Scope.

 Design and construction of a new overflow from Golden Island Pumping Station to the River Shannon;

 Decommissioning of the existing pumping stations at West Bank and Coosan West (both sub and superstructures);

 Demolition, decommissioning and disposal of the existing West Side and Abbey Road pumping stations (both sub and superstructures);

 Decommissioning of the existing Golden Island pumping station substructure and conversion of ground floor into open-plan storage area;

Awarded to:
16/062 - Athlone Main Drainage – Contract 2 - Networks
Ward & Burke Construction ltd, Kilcolgan (IE)
Download full details as .pdf
The Buyer:
Irish Water
CPV Code(s):
44611000 - Tanks
45221230 - Shafts
45221240 - Construction work for tunnels
45221247 - Tunnelling works
45232400 - Sewer construction work