Main quantities in the course "Roof work of existing buildings 004 and 005
(Swedish and Bux tree cultivation)":
- Demolition of roof covering with UK (unencumbered): approx. 307 m2
- New installation of corrugated fibre cement roofing with UK: approx. 307 m2
- Plumbing work, gutter mounting plate, hanging gutter: approx. 50
- Regenfallrohr DN70: ca. 31 m
- New installation of roof light strip l/w approx. 3, 75/1.10m, h= 55 cm: 1 piece
The service should also be processed as part of the electronic measurement, invoice and supplementary check (GAEB interface).
A written request for the documents is to be avoided.
These are provided exclusively digitally and free of charge via www.subreport.de/E11141764! ATTENTION! We recommend that you do not download the tender documents until you have registered. If the tender documents are downloaded without registration, there will be no automatic information about changes or bidder requests. The collection of information about changes is then the sole responsibility of the respective bidder!
Offers or requests to participate are to be submitted electronically via the function "Request for participation / submit offer" via: www.subreport.de
All further information is available at: http://www.ladadi.de/ausschaltungen
Main quantities in the course "Roof work of existing buildings 004 and 005
(Swedish and Bux tree cultivation)":
- Demolition of roof covering with UK (unencumbered): approx. 307 m2
- New installation of corrugated fibre cement roofing with UK: approx. 307 m2
- Plumbing work, gutter mounting plate, hanging gutter: approx. 50
- Regenfallrohr DN70: ca. 31 m
- New installation of roof light strip l/w approx. 3, 75/1.10m, h= 55 cm: 1 piece
The service should also be processed as part of the electronic measurement, invoice and supplementary check (GAEB interface).
Start of execution:
Within 12 working days of receipt of the request by the Client, the request is expected to be received by the Contractor by 22.12.2023.
Execution end:
Within 60 working days of the deadline for the start of execution ticked above.
Single deadlines:
-Roofer SWB expected 7.-14 KW 2024
-Roofer BXB expected CW 3-14 2024
Security for the fulfillment of the contract is in the amount of 5.0 percent. H. the order amount (including sales tax, without supplements), provided that the order amount is at least 250,000 euros without sales tax.
The security to be provided for claims for defects amounts to 3.0 percent of the settlement amount (including sales tax), including added supplements. Return date for unexplored security for claims for defects (§ 17 paragraph 8 no. 2 VOB/B): 4 years