This market is related to the renovation and compliance of a central production unit (cold link) to be operational by mid-March.
The special technical work concerns a new complete installation since:
- the existing gas pressure booth,
- the existing high voltage booth (compliance).
The technical work focuses essentially and non-exhaustively on:
1) HVAC:
- a hygienic ventilation installation,
- a tertiary ventilation system for hoods,
- a hot water heating and sanitary installation,
- a softened water production,
- the entire sanitary network situated above the floor slab,
A direct expansion cold production for a sheathed battery;
2) Electricity:
- a new complete high / low current installation,
- centralized fire detection,
- a CCTV installation / access control / anti-intrusion.
The "architecture" works concern the restructuring of the building whose internal demolitions have already been completed. They relate, in a non-exhaustive way, to:
- T0 - Site installation,
- T1 - Disassembly and demolitions,
- T2 - Structural elements:
- creation of a hopper for a freight elevator,
- closing skylight hoppers,
- T3 - Roofing work:
- realization of new DEP,
- insulation and sealing works,
- T4 - Closing elements and exterior joinery,
- T5 - Elements of closures and interior finishes,
- various partitions,
- T6 - Sanitary,
- T8 - Paint elements / surface treatments:
- floor and wall coverings,
- T9 - Roads - Networks - Miscellaneous:
- D - Preparations and selective demolitions,
- E - Earthworks,
- F - Sub-foundations and foundations,
- G - Coatings,
- I - Drainage and draining.