For the probstei community school in Schönberg, the new construction of a three-field sports hall was approved, which after completion replaces a demolished existing hall. On a bend-bordered meadow area adjacent to the school grounds, the new hall building with a floor area of approx. 2,700 m
The new sports hall will consist of a three-field sports hall, in which mainly movement games, running and ball sports will take place, as well as a gym and a fitness room for stationary equipment on the 1st floor. While the technical adjoining rooms and changing rooms are located on the ground floor, on the 1st floor visiting toilets, further adjoining rooms and the entrances to the spectator area of the gym and the spectator stands of the Dreifeldhalle with approx. 470 seats and additional wheelchair areas are arranged. A staircase opens up the 1st floor and the ventilation centre as a staggered floor on the 2nd floor.
Roofing work for the new construction of a sports hall.
Dimensions approx. 70 x 40 m
Room height approx. 11.00 m
Roof areas : approx. 2800 m2
Consisting of trapezoidal sheet metal work as covering on gable roof truss trusses, wood glue binders
Insulation with MW — accessible, pressure-resistant in partial areas
Slope insulation MW roof waterproofing based on bitumen
RWA ca 12 pcs
Plumbing — downspouts, pre-weathered, attic covers and flat roof drains
Planned construction time approx. 3 - 4 months