The primary and community school in Pönitz will be expanded by a new building with approx. 1,800 sqm GFA.
The three-storey new building will be built in solid construction (Stb /MW). The scope of the course is roughly summarized below:
- Aluminum PR facades: 2 pcs
- Aluminum tubular frame doors outside: 11 pcs
- Aluminum tubular frame doors inside: 31 pcs
- Aluminium windows inside: 11 pcs
- Aluminium windows outside: 1 pc
- Other: Top door closers, hold-open systems, ceiling smoke detectors, hand releases, push knob sets, handle bars, doorstoppers floor/wall
- Sheet metal cladding opening reveals/lintel: approx. 868 m
- Insulation and sheet metal cladding: approx. 63 sqm
more details in the specifications