Vibratory plug compaction in geotechnical hazard areas, construction site clearance, earthworks, monitoring.
- the work is carried out in geotechnical restricted areas at risk of settlement flow;
- Setting up and maintaining the construction site - approx. 21 months;
- Removal of wood by forest mulching - approx. 14 700 m
- Pre-drilling - approx. 40 starting points up to 14 m deep;
- Vibratory plug compaction approx. 1,990 starting points up to 25 m deep, area approx. 20,000 m
- Addition volume of tamping material approx. 33,000 m
- Earthworks - approx. 60,000 m
- Exposure of the gas pipeline (out of operation) - approx. 16 m in length, dismantling is carried out by the operator, the bidder is responsible for coordination;
- In addition, construction site clearing work, evidence preservation, ordnance detection, traffic safety, monitoring, surveying, quality assurance, fence work, disposal services, public appointment, documentation (for more details see list of services).