Sewer cleaning and visual inspection of drainage pipes at landfills in the district of Esslingen
Cleaning and TV inspection work at the Katzenbühl landfill, EsslingenThe subject of the contract is the annual cleaning (high-pressure flushing), inspection (TV examination) and creation of elevation and temperature measurement profiles for pipes made of PE-HD SDR 11 — SDR 17 or PVC, DN 100 — DN 600 approx. 8 000 m pipes made of stoneware, concrete DN 100 — DN 800 approx. 2,130 m approx. 90 ducts up to 10m depth, approx. 7 sludge traps, 1 piece Seachate retention basin approx. 450 m3
Cleaning and TV inspection work at the Weißer Stein landfill, PlochingenCleaning (high-pressure flushing), inspection (TV examination) and creation of altitude and temperature measurement profiles.
pipes made of HDPE, GRP inliner, stoneware, cast iron and concrete, DN 50 — DN 800, approx. 7,800 m,
cleaning of pipes within the dome PVC DN 200 and PE-HD da 280 approx. 2 000 m,
Approx. 74 pieces cleaning and inspection of shafts up to 30 m depth, 60 m3 reservoir, settling pool 152 m3, rain basin RKB 58 approx. 30 m3, dole DN 1600/2000, inlet and outlet structure (260 m2), tire washing system.
Cleaning and TV inspection work at the Ramsklinge landfill, FilderstadtCleaning (high-pressure flushing), inspection (TV examination) as well as creation of elevation and temperature measurement profiles for pipes made of PE-HD SDR 11 and SDR 17, stoneware, cast iron and concrete, da 125 - da 400 approx. 3100 m, pressure test for PE-HD pressure pipe da 125, pipe length 1,700 m in 2 sections, approx. 37 pieces cleaning and inspection of manholes up to 3 m depth, 100 m3 reservoir, 2 piece storage basins 400 m3 each.
Cleaning and TV inspection work at the Hintere Halde landfill, OberboihingenCleaning (high-pressure flushing), inspection (TV examination) as well as creation of altitude and temperature measurement profiles Pipes made of PE-HD SDR 17 da 225 approx. 1,570 m, main collector PVC da 250 approx. 340 m, approx. 25 shafts up to 5 m deep and a measuring shaft with fixtures.
Cleaning and TV inspection work at the Blumentobel landfill, BeurenCleaning (high-pressure flushing), inspection (TV examination) and creation of altitude and temperature measurement profiles.
Domestic waste disposal: pipes made of GRP inliner, PE-HD (compact pipe) DN 250 approx. 5,406 lm, pipes made of PE-HD da250 perforated approx. 2,200 lm, approx. 115 pieces cleaning and inspection shafts.
Earth and rubble landfill: pipes made of PE-HD DA 280 — 2/3 perforated, D 300 cast pipes and pipes Auspe-HD da 355 perforated approx. 1100 lm, approx. 4 shafts.
other drainage pipes made of PE, stoneware, concrete approx. 200 lm, inspection drainages D 1 to D 9 approx.140 lm,
9 pcs bays
Cleaning and TV inspection work at the Federlesmahd landfill, Leinfelden-EchterdingenCleaning (high pressure flushing), inspection (TV inspection), pipes made of PE-HD 200 approx. 600 m, 8 shafts