Traffic safety work on the 6-lane extension of the BAB A 61 between AS Rheinböllen and T & R-Anlage Hunsrück over a length of approx. 2 km, including widening of 2 structures.
- Carry out 9 traffic safety measures of a longer duration (highway),
- carry out 9 traffic safety measures of a longer duration (federal / district road),
- approx. 17 000 m produce temporary marking (agglomerate),
- produce approx. 24 000 m of temporary marking (foil),
- approx. 18,000 m construction of transportable protective devices,
- 1 hour construction of a mobile traffic jam warning system,
- 1 600 d provision, maintenance and operation of a mobile traffic jam warning system.