The construction project includes the construction of the streets (N198) of the Etelä-Nummela workplace area (N198) in South Nummela.
construction of municipal engineering. The area is located south of the built-up settlement of Nummela and joins the
jaman to the city centre via Pillistöntie. A large business area is being formed in the planning area. In addition,
The area already has existing settlements.
The construction contract comprises the main street Hankasalontie and the related plot streets Rajakulmankuja, Kiilamäenkuja,
In accordance with the plans and tender documents for the construction of Loukokuja, Loukopolku and Kattilamäentie.
Hankasalontie is an illuminated street about 1.5 kilometers long. Hankasalontie serves as the main street of the area and across it.
The section consists of a 7.5-metre-wide carriageway, a separation/planting lane and a 4-metre-wide combined
sidewalk and bike path. On Hankasalontie, preparations are being made for a bus dealership, and the parking company serving the area
a pair of sacks is placed in the area between Rajakulmankuja and Kiilamäenkuja. In addition, at the end of the Hankasalons
There is a designated turning point, as well as a terminus for buses.
There are significant elevation differences in the area, and the streets are in some places even on high banks and deep cuts. Regional
The soil is varied, mainly rock, clay, sand moraine and loam. The design area is not located
in a classified groundwater area. A culvert is built under the rubbing salons, under which flows
groundwater formed in the area. There is a 110 kV power line and a 400 kV power line running in the area. In the case of rubbing salons,
tea will be built with an underground cable 2x110 kV line.
A water supply network will be built in the area for current housing and future operations in the workplace area.
In connection with the construction of the water supply network, a pressure sewer line will be built for the existing wastewater treatment system.
and pressure sewer reservations for the transfer of the wastewater treatment plant. Pressurised sewers and water supply
The previously planned transfer sewer line at the junction of Vanha Turuntie and Hankasalontie.
Loukokuja and Loukopolku have property-specific wastewater pumping stations. In the area will be built two Vihti
a wastewater pumping station built by water. One of the pumping stations is located on Hankasalontie about a pile
700 (JVP001). One of the pumping stations (JVP003) will be built near the turning point of Rajakulmankuja. Axil-
A wastewater treatment plant is planned at the end of the salons, where the area's wastewater will be treated.
The construction contract comprises the main street Hankasalontie and the related plot streets Rajakulmankuja, Kiilamäenkuja,
In accordance with the plans and tender documents for the construction of Loukokuja, Loukopolku and Kattilamäentie.