Quantities:
- 1 main building distribution,
- 10 floor distributions,
- 3 distributors in NWT rooms,
- approx. 60,000 m of cable up to 16 sqmm,
- approx. 1 900 m cable up to 150 sqmm,
- approx. 2,200 m cable tray,
- approx. 110 m riser,
- approx. 900 m parapet canal,
- approx. 1 200 LED lights,
- approx. 100 LED safety lights,
- approx. 100 LED pictograms,
- approx. 2,300 switch material,
- approx. 300 sensors,
- Execution in 3 construction phases:
—— Completion of BA 1 on June 24th, 2022
—— Completion of BA 2 on July 7th, 2023
- Completion of BA 3 on June 28, 2024
s. II 1.4).