Conversion of the former restaurant into a town hall as well as new construction of the community hall and the functional buildings
approx. 370 m fills joints of precast concrete elements
approx. 1,220 m² primer surfaces
approx. 720 m² primer plaster surfaces
approx. 1,280 m² primer drywall areas
ca. 1.260 m² Glasfasergewebe
approx. 2,390 m² painting walls
approx. 830 m² painting ceilings
approx. 560 m² exterior painting
approx. 15 m² floor coating
Execution Bürgersaal: Spatula work 30.01.2023 – 03.03.2023
Erstanstrich 25.04.2023 – 03.07.2023
Zweitanstrich 04.07.2023 – 31.07.2023
Execution of town hall: filler work 01.05.2023 – 16.06.2023
Erstanstrich 24.10.2023 – 05.01.2024
Zweitanstrich 15.01.2024 – 09.02.20243