Description:
Installation of photovoltaic microinstallations on public buildings in Sieradz - stage III

The subject of the contract is the design, delivery and execution of construction and installation works related to the execution of 6 photovoltaic microinstallations on public buildings with a capacity below 50 kWp each.

The contracting authority requires that as a result of the works, independent installations of photovoltaic generators are created, which will be installed on the roofs of buildings.

Władysław Reymont Primary School No. 1, 14 Kościuszki Street, 98- 200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 20.25 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

e) installation of GPWP, customization and agreement with the PPO security expert.

Władysław Reymont Primary School No. 1, 4 Rycerska Street, 98-200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 45.45 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

e) installation of GPWP, customization and agreement with the PPO security expert.

Maria Konopnicka Primary School No. 4, 18 A. Leśniewskiego Street, 98-200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 39.60 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

Maria Konopnicka Primary School No. 4, 30 Broniewskiego Street, 98-200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 29.70 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

e) installation of GPWP, customization and agreement with the PPO security expert.

Janina Majkowska Primary School No. 6, Uniejowska 199, 98-200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 40.05 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

e) installation of GPWP, customization and agreement with the PPO security expert.

Władysław Łokietek Primary School No. 9, 55 Łokietka Street, 98-200 Sieradz.

a) construction of a photovoltaic installation with a total capacity of min. 19.80 kWp,

b) construction of a smartmeter meter in the main switchboard, cooperating with the installed inverter with RS485 connection in order to monitor the production, consumption and transmission of energy to the energy operator,

c) installation of the system monitoring system via LAN/WI-FI network,

d) partial reconstruction and adaptation of the existing lightning protection system so that it protects the building and the built photovoltaic installation,

e) installation of GPWP, customization and agreement with the PPO security expert.

The full scope of the description of the subject of the contract can be found in SWZ.

Download full details as .pdf
The Buyer:
gmina Miasto Sieradz
CPV Code(s):
09332000 - Solar installation
45261215 - Solar panel roof-covering work
45300000 - Building installation work
45311100 - Electrical wiring work
45311200 - Electrical fitting work
45315100 - Electrical engineering installation works
45315300 - Electricity supply installations
45315600 - Low-voltage installation work
45317300 - Electrical installation work of electrical distribution apparatus
71320000 - Engineering design services