Screed work Scope of the works: - Single-layer bituminous waterproofing: 1,500 m2; - Cement screeds: 2,640 m2; - Light cement screeds: 1,525 m2; - PIR panels: 1,480 m2; - Sound insulation in mineral wool: 4,795 m2; - Cement screeds: 4,225 m2; - Cement screeds with quartz wear layer: 240 m2. Start of work; scheduled for March 2024 Duration of works: 100 working days
Screed work Scope of the works: - Single-layer bituminous waterproofing: 1,500 m2; - Cement screeds: 2,640 m2; - Light cement screeds: 1,525 m2; - PIR panels: 1,480 m2; - Sound insulation in mineral wool: 4,795 m2; - Cement screeds: 4,225 m2; - Cement screeds with quartz wear layer: 240 m2. Start of work; scheduled for March 2024 Duration of works: 100 working days